Condition-based maintenance (CBM): monitoring techniques and the P-F curve

Reliability9 min readUpdated 2 November 2026By TimeQeeper

Condition-based maintenance (CBM) is maintenance you perform based on the actual condition of an asset rather than a fixed calendar. With condition monitoring you measure one or more indicators that say something about a machine's health, such as vibration, temperature or oil contamination, and you act only when those indicators show that something is changing. As long as the condition is good, you keep the machine running. The principle is straightforward: an asset that measurements show to be healthy does not need to be opened up or replaced as a precaution.

What sets CBM apart from other strategies

Maintenance strategies form a spectrum. At one end sits corrective maintenance: you repair only after something has failed. At the other end sits preventive maintenance on fixed intervals: every so many running hours or months you replace a component regardless of its real state. Both have a weakness. Corrective maintenance accepts the failure and its consequences; interval-based preventive maintenance replaces parts that are often still perfectly fine, while missing the failures that arise outside the schedule.

CBM is a form of preventive maintenance that acts on the measured condition rather than at a fixed interval. You react to a threshold that is being crossed now: the vibration reading is too high, so you schedule an intervention. Predictive maintenance goes a step further and extrapolates the measured condition to an expected point of failure, so you can plan the intervention ahead; that article also explains exactly how the two differ. The basis of this classification is covered in preventive vs corrective maintenance. A broader background on the concept is available on Wikipedia's condition-based maintenance page.

The P-F curve: the heart of CBM

To understand why condition monitoring works, you need to know how failure develops over time. Almost no component goes from "fully healthy" to "broken" in a single step. There is usually a period in which the condition deteriorates measurably before the function actually gives out. You describe that development with the P-F curve.

The curve has two points. P is the point of potential failure: the first moment at which a suitable measurement method can detect that something is starting to go wrong. Think of a bearing that begins to show a subtle vibration pattern, or oil in which the first wear particles appear. At that point the machine still works normally, but decay has begun and it is detectable. F is the point of functional failure: the asset no longer does what it is supposed to do.

The P-F curve for the bearing example in the text. P: the first moment a measurement can see the decay; F: functional failure. Of the 2 months in between, 2 weeks go on preparation; measure at least twice in the 6 weeks before.ConditionTimeP: potential failurefirst moment a measurement can detect it;the machine still works normallyF: functional failurethe asset no longer doeswhat it is supposed to donothing to see yetP-F interval: 2 monthsbearing defect, worst case6 weeks to catch Pmeasure at least 2×: every 3 weeks2 weeksto preparemeasurement, every 3 weeks
The P-F curve for the bearing example in the text. P: the first moment a measurement can see the decay; F: functional failure. Of the 2 months in between, 2 weeks go on preparation; measure at least twice in the 6 weeks before.

The time between P and F is called the P-F interval. This interval is the core of every CBM decision, because it determines how often you have to measure. As a rule of thumb, your inspection interval should be no more than half the P-F interval, which gives you at least two chances to detect P. On top of that, the time left between detection and F, the net P-F interval, must be long enough to plan the intervention, order parts and carry out the work. An example: if, in the worst case, a bearing defect announces itself two months before failure and you need two weeks to prepare the intervention, six weeks remain to catch P. Measure at least twice in that window, so at least every three weeks. Measure once every six months and you are likely to miss P and be caught out at F. Measure daily and you measure far more often than needed, wasting capacity.

Two things matter here. First, the P-F interval depends on the measurement method. Vibration analysis often detects a bearing defect much earlier than a technician checking by touch or ear; a more sensitive method effectively lengthens the usable interval. Second, the interval is an estimate based on failure behaviour and experience, not an exact number. So base your inspection interval on the shortest realistic version of it, with a margin.

Condition monitoring: what it is and which techniques to use

Condition monitoring is the periodic or continuous measurement of an asset's condition, so you can see when it changes. Condition-based maintenance is what you do with the result: planning the intervention when the measurement calls for it. Monitoring without follow-up only produces graphs. The general approach to setting up such a programme for machines is described in ISO 17359.

CBM depends on choosing an indicator that reliably responds at P. These are the techniques you will meet most often:

TechniqueWhat you measureWhat it findsTypical use
Vibration analysisvibration level and spectrumimbalance, misalignment, bearing wearmotors, pumps, fans, gearboxes
Thermographythermal image, temperaturefriction, overload, poor contactselectrical panels, bearings, mechanical parts
Oil analysiswear particles, viscosity, contaminationinternal wear, aged or contaminated oilgearboxes, hydraulics, engines
Ultrasoundhigh-frequency soundleaks, incipient mechanical problemscompressed air, steam, bearings
Motor currentcurrent drawn by the motoroverload, changed loadelectric motors
Thickness measurementremaining wall thicknesscorrosion and erosionboiler tubes, pipework, tanks
Visual inspectionsight, hearing, touchleaks, loose parts, cracksany installation

The choice of indicator depends on the failure mechanism you want to catch. A single machine can justify several indicators at once, because different failure modes announce themselves in different quantities.

Vibration analysis

Vibration is the standard for rotating equipment such as motors, pumps, fans and gearboxes. Vibration spectra reveal imbalance, misalignment and bearing wear at an early stage. Always measure at the same points and at a comparable load, otherwise your readings can't be compared. ISO 20816-1 gives general guidelines for measuring and evaluating machine vibration.

Temperature and thermography

Elevated temperature points to friction, overload or poor lubrication. Thermography makes anomalies visible in electrical panels and mechanical components: you scan with a thermal camera while the equipment runs under load, so nothing has to be stopped. The general procedures are set out in ISO 18434-1.

Oil and lubricant analysis

Counting and analysing wear particles, viscosity and contamination gives insight into the internal condition of gearboxes, hydraulics and engines. Always take the sample at the same point and under the same conditions; the trend across several samples says more than one result. This ties in with your lubrication schedule, which already fixes the lubrication points and intervals.

Ultrasound and acoustics

Abnormal sound patterns, including ultrasonic, indicate leaks in compressed-air and steam systems or incipient mechanical problems. An ultrasonic meter picks up high-frequency sound you can't hear yourself, which also makes it usable in a noisy hall.

Other techniques

Depending on the asset, current draw, pressure, flow, and corrosion or wall-thickness measurements come into play. Wall-thickness surveys, for example, are the core of boiler maintenance in a waste-to-energy plant. The cheapest technique is still the fixed inspection round: someone who walks past the same pump every week hears and sees many anomalies early.

Periodic measurement or continuous monitoring

Periodic readings, with a handheld device or along a fixed route, are often enough when the P-F interval is weeks or months. Fixed sensors make most sense when deterioration is fast, the consequences are serious or the location is hard to reach. Always record the result against the asset, for example as a condition class in asset management software, so the trend stays visible across years and survey crews.

Running hours: use, not condition

Running hours are not a condition indicator: they measure use, not condition. They are useful context, though. They put measurements next to actual use and drive usage-based tasks, such as an inspection or measurement after a set number of hours. How to measure and use them is covered in monitoring running hours with IoT sensors; how TimeQeeper does it is on the page about running hours and monitoring.

When CBM pays off, and when it does not

CBM is not a goal you apply to every asset. It delivers the most under a number of conditions. There must be a failure mechanism that develops gradually and measurably, with a P-F interval long enough to react to. The failure must also carry consequences that justify the measurement effort: unplanned downtime, safety or environmental risk, or high follow-on damage. And a practical, affordable measurement method must exist that reliably picks up P.

If one of those conditions is missing, another strategy is often better. For failure mechanisms without a warning period, where the asset fails suddenly, condition monitoring adds little. If that failure is age-related, replacement at a fixed interval fits; if it is random, what remains is redesign, deliberately running to failure or, for hidden failures, a periodic functional test. For parts that are cheap, quick to replace and fail without notable consequences, deliberate corrective maintenance is often the most sensible choice: you run it to failure and replace it then. And where a fixed interval is simple, cheap and proven safe, there is no need to add the complexity of continuous measurement.

In practice you use the strategies side by side. You decide per asset and per failure mode which approach fits, usually based on criticality and failure behaviour. RCM offers a structured way to make that choice. CBM is then the tool you deploy where gradual, measurable decay coincides with consequences you would rather not wait for.

Frequently asked questions

What is the difference between condition monitoring and condition-based maintenance?

Condition monitoring is the measuring: you follow an asset's condition through vibration, temperature, oil analysis or other indicators. Condition-based maintenance is the strategy built on top of it: you plan the intervention when the measurement calls for it. Monitoring without follow-up produces no maintenance, and planning without measurements is simply preventive maintenance at a fixed interval.

Is condition monitoring the same as predictive maintenance?

No. Condition monitoring supplies the measurements and shows where things stand now. Predictive maintenance uses the trend in those measurements to forecast when a limit will be reached. Without condition monitoring there is nothing to forecast from, but not every form of monitoring has to lead to a forecast: a threshold is often enough.

How do I decide how often to measure?

You derive it from the P-F interval: the time between potential failure (P) and functional failure (F). As a rule of thumb, measure at least twice within that interval, so with an inspection interval of no more than half of it, and keep enough time after detection to prepare the intervention. A shorter warning period therefore requires more frequent measurement.

Do I need expensive sensors for CBM?

Not necessarily. CBM starts with choosing the right indicator, not the most expensive technology. Periodic manual readings, oil samples or route-based vibration measurements already deliver a lot. Fixed sensors and continuous monitoring make sense when the P-F interval is short or the failure consequences are high.

Ready for more control over your maintenance?

Book a tailored demo. We'll show how TimeQeeper fits your machines, way of working and team, and we'll get in touch quickly.

We use functional storage and cookieless statistics. With your consent, LinkedIn measures visits and demo requests and helps us show relevant ads. LinkedIn may link this data to your profile.

Functional storage and cookieless statistics
Always available
LinkedIn marketing
Disabled

Your choice lasts 180 days. Declining does not affect the website or your demo request. You can change your choice here at any time.

Privacy statementCookie statement