Skip to content
TimeQeeper

NEN 3140 inspection: what it is, how often and who may inspect

Safety10 min readUpdated 15 November 2026By TimeQeeper

A NEN 3140 inspection is the periodic inspection of an electrical installation, or of electrical work equipment, under NEN 3140, the Dutch standard for the safe operation of low-voltage installations. The inspector carries out a visual check and measures and tests: does the residual current device (RCD) in sub-distribution board OV-02 trip when tested, and is the earth connection of the cable reel from the workshop intact? The findings go into a report, and defects must be repaired as soon as possible. How often this happens is decided by the installatieverantwoordelijke, the person nominated to be in control of the installation, based on the risks; Dutch law sets no fixed interval.

What is NEN 3140?

NEN 3140 is published by NEN, the Dutch standards body. Its full title, Bedrijfsvoering van elektrische installaties - Laagspanning, translates as operation of electrical installations, low voltage. Operation covers the use, maintenance, inspection and management of installations and work equipment, and any work on, with or near an installation. The standard applies up to 1,000 volts AC and 1,500 volts DC, both to the fixed installation of a building or plant and to electrical work equipment such as tools and extension leads.

NEN 3140 is based on the European standard EN 50110-1. The Dutch standard takes over the European provisions and adds to them, so that every relevant requirement for low voltage is in one document. High voltage is covered by NEN 3840, and medium voltage, such as a site's own 10 kV room, counts as high voltage under Dutch law. NEN 1010 is about installing a new installation; NEN 3140 is about operating one that is already there.

NEN 3140 applies in the Netherlands; other countries have their own inspection rules. NEN itself points out that tools tested under NEN 3140 and then used in Germany must be inspected under German rules.

The current edition is NEN 3140:2011+A3:2019. A draft of a new edition appeared in 2026; until it is final, the 2019 edition applies.

Is a NEN 3140 inspection mandatory?

Not literally. NEN 3140 is a standard, not a law, and the law does not mention it. The Dutch Working Conditions Decree (Arbobesluit) does set requirements that a periodic inspection logically meets:

  • Article 3.4 (Dutch text): electrical installations are designed, installed and maintained so that safe use is ensured as far as possible, with up-to-date circuit diagrams (small low-voltage installations excepted).
  • Article 3.2: protective provisions are checked regularly and defects repaired as soon as possible.
  • Article 3.5: electrical work that can be dangerous is carried out by competent, adequately instructed and authorised employees.
  • Article 7.4a: work equipment that can deteriorate is inspected as often as necessary, by a competent person, with written evidence kept at the workplace.

NEN puts it like this: strictly speaking, applying NEN 3140 is not compulsory, but employers cannot avoid it. You may meet the duty of care another way, but after an incident you then have to show that your own approach is sufficient. In its inspection module, the Netherlands Labour Authority (Nederlandse Arbeidsinspectie) describes NEN 3140 as the state of the art; deviating from it is allowed if you achieve a comparable level of safety. If an inspector sees shortcomings in an installation, they may ask for the inspection report. Which other inspections apply is covered in statutory inspections.

Installation or work equipment: what is inspected?

NEN 3140 distinguishes two kinds of object. The installation is everything that is permanently installed; work equipment is any machine, appliance or tool that you connect to it. In the UK, testing portable equipment like this is known as portable appliance testing (PAT); in the Netherlands, such testing usually follows NEN 3140.

Electrical installationElectrical work equipment
ExamplesMain distribution board, sub-distribution boards, cables, socket outlets, lightingDrill, angle grinder, extension lead, cable reel, battery charger
Legal basisArbobesluit art. 3.4, with 3.2 for checks and repairArbobesluit art. 7.4a (inspection) and 7.5 (maintenance)
What happensVisual inspection plus measuring and testing, possibly sampling the final circuitsVisual check and measurements per item: pass or fail
How oftenInterval based on risk, set by the installatieverantwoordelijkeAs often as necessary, with once a year as a minimum

For the installation, the inspector checks whether it still meets the safety requirements under which it was installed. They look for damage, oversized fuses and the state of the circuit diagrams, and measure, among other things, the protective conductors, insulation resistance, earth electrode resistance and the operation of the RCDs.

For work equipment, the tester looks at the housing, cable and plug and measures, among other things, the protective conductor (on appliances with an earth connection), the insulation resistance and the leakage current. The test is about electrical safety: according to NEN, it says nothing about whether the appliance works properly.

Since 2020 there has also been a European standard for the recurrent testing of electrical equipment, EN 50699, alongside the requirements in NEN 3140 itself. Ask for the report to state which standard the testing followed.

How often do you need to inspect?

For installations, the law sets no interval, and NEN 3140 makes it depend on the risks. According to the Labour Authority, the installatieverantwoordelijke records, with reasons, what is inspected and when. That depends on the environment (dust, moisture, vibration), the use, the age and condition of the installation and earlier findings. An annex to NEN 3140 gives a method with weighting factors for the interval, and another annex a method for sizing a sample. In practice you will come across intervals of around five years for installations in a normal environment, and shorter ones in harsh conditions or for an old installation. For the visual inspection, the rule since 2019 is that the installatieverantwoordelijke records how often it takes place; if nothing has been recorded, it stays at once a year.

For work equipment, article 7.4a says as often as necessary to keep it in good condition. According to the explanatory notes to the decree, once a year can be taken as the minimum; with intensive use or in a harsh environment, you test more often. After an exceptional event, such as a modification, an accident or a long period out of use, you test again.

Who may carry out a NEN 3140 inspection?

Someone who is competent and designated to do it, whether you call them an inspector or a tester. The law requires competence (articles 7.4a and 3.5), and NEN 3140 sets this out in roles. The employer, or whoever they delegate the task to, designates people in writing, stating the installations and the work the designation (aanwijzing) covers. According to NEN, a designation cannot rest on a completed course alone: experience and the working conditions matter at least as much.

RoleWho it isRole in inspections and tests
Installatieverantwoordelijke (IV)Nominated person in control of the electrical installationRecords with reasons what is inspected and when, and makes sure defects are dealt with
Werkverantwoordelijke (WV)Nominated person in control of a work activityPrepares work such as measurements in a distribution board and makes sure it runs safely
Vakbekwaam persoon (VP)Skilled person: can assess hazards and take measures independentlyInspects, measures and repairs within their designation
Voldoende onderricht persoon (VOP)Instructed person: instructed for specific tasks, their risks and the precautionsCarries out only the tasks in their designation, under supervision where needed
LeekOrdinary person: not electrically skilled and not designatedDoes not work on the installation, unless an authorised person has made it dead and safe

Inspecting an installation calls for a skilled person with experience in inspection and measurement. Electrical work equipment is tested by someone who has been trained for those measurements and designated to carry them out; whether that fits within an instructed person's designation is for the employer to judge.

Your own staff or an inspection company: the employer chooses, and the responsibility stays with them. With a company certified under the Dutch SCIOS scheme, you can check the inspector's authorisation on the SCIOS website.

What goes into an inspection report?

Make sure the report states at least:

  • which installation or which items of equipment were inspected, and what was not;
  • the date, the inspector, the test instruments and the readings per distribution board or item;
  • for each defect, the location (board and circuit), a description, a photo and the severity;
  • for work equipment, for each item: pass or fail.

Ask the inspector to separate defects, which must be repaired, from recommendations. Agree that a dangerous situation, such as exposed live parts, is reported immediately, so that you can make that part of the installation safe straight away.

Each item of electrical work equipment must be demonstrably approved for use. The standard does not prescribe how, and there is no official NEN 3140 inspection sticker. A label showing the next test date is a common way. Keep reports with the asset they belong to, as described in technical document control.

What does a NEN 3140 certificate mean?

When people talk about a NEN 3140 certificate, they mean one of three things:

  1. A training certificate. After a course, for example for VOP or VP, you receive a certificate of attendance. According to NEN it has no validity period of its own, and it is not a designation: that comes from the employer.
  2. Proof of inspection. For an installation that is the inspection report, for work equipment the test record or a label. NEN itself does not issue NEN 3140 inspection certificates.
  3. A certificate held by the inspection company. An inspection company can be certified under the SCIOS scheme, supervised by a certification body.

NEN 3140, SCIOS Scope 8 and Scope 10: what is the difference?

SCIOS manages a Dutch certification scheme for inspection companies, which for electrical equipment includes these scopes, among others:

  • Scope 8, electrical installations. Scope 8 PI is the periodic inspection under NEN 3140. Scope 8 EBI is the inspection after completion or before you move into a building, based on NEN 1010 part 6.
  • Scope 9, electrical work equipment, also based on NEN 3140.
  • Scope 10, electrical equipment and fire risk, under NTA 8220. Fire insurers may make this inspection by a certified company a policy condition.

The difference lies in the purpose. A NEN 3140 inspection, with or without Scope 8 or 9, is about safe use and preventing injury. Scope 10 looks at fire risk, and according to SCIOS (in Dutch) an inspection based on NEN 3140 is not enough for that. A NEN 3140 inspection does not have to be carried out by a certified company; certification does fix requirements for the working method and the inspectors. Check your policy to see which inspection your insurer asks for.

How to organise NEN 3140 inspections in your maintenance

Treat the inspections as a cycle of five steps, each with an owner.

The NEN 3140 inspection as a cycle of five steps: take stock, inspect, report, repair and plan again, with the role responsible for each step. The inspector reports a dangerous situation immediately, so that it can be made safe straight away.NEN 3140installations andwork equipmentTake stockeverything in one overviewIV records interval and reason1Inspectvisual check, measuring, testingVP or designated tester2Reportreadings, defects and severityReport goes to the IV3Repairwork order, retest, sign offVP repairs, IV oversees4Plan againadjust the interval to the findingsIV, with reasons5next roundDangerous situation?report at once and make safe
The NEN 3140 inspection as a cycle of five steps: take stock, inspect, report, repair and plan again, with the role responsible for each step. The inspector reports a dangerous situation immediately, so that it can be made safe straight away.
  1. Take stock. Put all installations and work equipment in one overview: distribution boards as positions in your asset register, tools as individual items with their own number. The IV records the interval for each item, with the reason.
  2. Inspect. Add every inspection to your maintenance plan as a recurring task. Agree which circuits may be switched off and arrange safe isolation for measurements; see safe maintenance with LMRA, LOTO and permits to work.
  3. Report. The report goes to the IV. Record each finding separately, as described in managing maintenance contractors.
  4. Repair. Create a work order for each defect, with a deadline that fits its severity. A VP repairs, retests and signs off; the IV makes sure every defect is dealt with. Failed work equipment stays out of use until it has been repaired and tested again.
  5. Plan again. After each round, check whether the interval is still right. If defects recur, shorten it; if an installation stays fault-free for years, the IV can extend the interval, with reasons.

You can see what a recurring round that creates its own work order looks like under maintenance rounds.

Example: a main distribution board, sub-boards and a tool rack

At a metalworking company, main distribution board HV-01 feeds four sub-distribution boards: OV-01 in hall A, OV-02 in the dusty grinding area in hall B, OV-03 in the workshop and OV-04 in the office. The installation is twenty years old. In the workshop there is a rack of 24 items of work equipment: 20 tools and extension leads, and 4 cable reels that are also used in hall B. The IV records this plan:

ItemWhatInterval in this exampleWhy
HV-01 and OV-01 to OV-04Visual inspectionEvery yearSpot defects in dusty hall B quickly
HV-01 and OV-01 to OV-04Measuring and testing, final circuits by samplingEvery three yearsInstallation twenty years old, dust in hall B
20 tools and extension leadsTest per itemEvery yearMinimum from the explanatory notes, normal use
4 cable reelsTest per itemEvery six monthsHeavy use in hall B

During the measurement round in March, the inspector finds four points:

  • OV-03: a cover plate is missing and live parts can be touched. The inspector reports this immediately; a VP fits a cover the same day.
  • OV-02: an RCD does not trip when tested. Serious: replace within a week and retest.
  • OV-04: the circuit chart no longer matches after a refurbishment. Update within a month, because article 3.4 requires up-to-date diagrams.
  • Recommendation: dust in the cable trays in hall B, to be cleaned at the next maintenance shutdown.

When the rack is tested, 2 of the 24 items fail: an angle grinder with a damaged cable and a cable reel whose protective conductor resistance is too high. They are labelled as failed and taken out of the rack: the reel is replaced, and the grinder gets a new cable and is tested again.

Six weeks later the IV goes through the list: every defect has been signed off, with a photo or a reading. Because two defects relate to hall B, they will check after the next round whether the intervals there should be shorter.

Frequently asked questions

What do VP and VOP mean in NEN 3140?

VP stands for vakbekwaam persoon, a skilled person: someone who can independently assess the hazards of electricity and take measures. VOP stands for voldoende onderricht persoon, an instructed person: someone who has been instructed for specific tasks. Both roles are given through a written designation by the employer.

Can you test electrical tools yourself?

Yes, as long as the tester is competent. One of your own employees can do it if they have been trained for the measurements, use a suitable test instrument and have been designated for this work. Record the results per item: the evidence must be kept at the workplace.

How long is a NEN 3140 inspection valid?

There is no fixed validity. An inspection shows that something was in order on that day, and it holds until the next recorded date, as long as nothing happens. If an appliance is dropped or a cable is damaged, you assess it again.

What is the difference between NEN 3140 and NEN 1010?

NEN 1010 sets the requirements for installing a low-voltage installation, including the inspection on completion. NEN 3140 covers operation after that: working safely, operating the installation and inspecting it periodically.

Ready for more control over your maintenance?

Book a tailored demo. We'll show how TimeQeeper fits your machines, way of working and team, and we'll get in touch quickly.

We use functional storage and cookieless statistics. With your consent, LinkedIn measures visits and demo requests and helps us show relevant ads. LinkedIn may link this data to your profile.

Functional storage and cookieless statistics
Always available
LinkedIn marketing
Disabled

Your choice lasts 180 days. Declining does not affect the website or your demo request. You can change your choice here at any time.

Privacy statementCookie statement